Q4 2024 Production Report and 2025 Guidance
Kenmare Resources plc
(“Kenmare” or the “Company” or “the Group”)
20 January 2025
Q4 2024 Production Report and 2025
Guidance
Kenmare Resources plc (LSE:KMR, ISE:KMR), one of
the leading global producers of titanium minerals and zircon, which
operates the Moma Titanium Minerals Mine (the "Mine" or "Moma") in
northern Mozambique, is pleased to provide a trading update for the
full year 2024 and the fourth quarter ending 31 December 2024 (“Q4
2024”) and production and operating cost guidance for 2025.
Statement from Tom Hickey, Managing
Director:
“Kenmare delivered a strong finish to 2024,
exceeding the midpoint of our production guidance for ilmenite and
the upper end of the guidance ranges for all other products. We
also passed the milestone of two million hours worked without a
Lost Time Injury in late December. These achievements are testament
to the hard work and commitment of our team at site during a
challenging period.
In 2024 we paid $48 million in dividends and
invested over $140 million in capital programmes, primarily for the
upgrade and transition of our largest mining plant to Nataka. Our
balance sheet remains strong and we expect our full year 2024
dividend to be towards the upper end of our payout policy of 20-40%
of profit after tax.”
Overview
- Lost Time Injury Frequency Rate (“LTIFR”) of 0.06 per 200,000
hours worked to 31 December 2024 (31 December 2023: 0.15), with
zero Lost Time Injuries (“LTIs”) in Q4 2024
- Kenmare exceeded the midpoint of production guidance for
ilmenite and the upper end of the guidance range for primary
zircon, rutile and concentrates in 2024
- Heavy Mineral Concentrate (“HMC”) production of 1,446,600
tonnes in 2024, broadly in line with 2023, due to record excavated
ore tonnes offset by lower ore grades
- Ilmenite production of 1,008,900 tonnes in 2024, a 2% increase
year-on-year (“YoY”), due to higher ilmenite content in the HMC and
stronger recoveries
- Shipments of finished products of 1,088,600 tonnes in 2024, up
4% YoY. Shipments in H2 2024 were significantly stronger than in
H1, as expected, with 611,000 tonnes shipped
- Interim 2024 dividend of USc15.0 per share paid in October 2024
and full year 2024 dividend expected to be at the upper end of the
payout ratio of 20-40% of profit after tax
- Net debt of $24.8 million (2023: $20.7 million net cash) due to
on-going development capital expenditure
- Demand for all of Kenmare’s products remained robust in 2024
and sales are expected to continue to exceed production in
2025
- Ilmenite production guidance for 2025 is 930,000 to 1,050,000
tonnes
- Expenditure on development projects and studies is expected to
be approximately $155 million in 2025. The Wet Concentrator Plant
(“WCP”) A project remains on budget, with a total cost estimate of
$341 million
- The process for the renewal of Moma’s Implementation Agreement
(“IA”) continues to progress and the Government of Mozambique has
confirmed that Kenmare’s rights under the IA remain in place until
the renewal is completed
- As previously announced, James McCullough has been appointed as
Chief Financial Officer and he will join Kenmare on 1 May 2025
Operations update
Operational results for the Moma Mine in Q4 and
full year 2024 were as follows:
|
Q4 2024 |
vs Q4 2023 |
vs Q3 2024 |
2024 |
vs 2023 |
tonnes |
% change |
% change |
tonnes |
% change |
Excavated ore1 |
10,333,000 |
11% |
-7% |
41,248,000 |
7% |
Grade1 |
4.96% |
3% |
31% |
4.17% |
-5% |
Production |
|
|
|
|
|
HMC produced |
432,300 |
8% |
22% |
1,446,600 |
0% |
HMC processed |
442,100 |
11% |
24% |
1,449,200 |
0% |
Ilmenite |
307,400 |
14% |
19% |
1,008,900 |
2% |
Primary zircon |
14,700 |
5% |
1% |
50,500 |
-1% |
Rutile |
2,900 |
38% |
0% |
9,800 |
17% |
Concentrates2 |
11,200 |
7% |
-17% |
46,100 |
1% |
Shipments |
308,300 |
-5% |
2% |
1,088,600 |
4% |
- Excavated ore and grade prior
to any floor losses.
- Concentrates include secondary
zircon, mineral sands concentrate and a new concentrates
product.
Kenmare passed the milestone of two million
hours worked without an LTI in early January 2025. There were no
LTIs in Q4. Two LTIs were recorded in the 12 months to 31 December
2024, compared to five in 2023, resulting in an improved rolling
12-month LTIFR of 0.06 per 200,000 hours worked (31 December 2023:
0.15).
HMC production in Q4 2024 was 432,300 tonnes, an
8% increase YoY. This was due to a 11% increase in excavated ore
tonnes as a result of excellent throughputs and operating time at
WCP B and C, and a 3% increase in ore grades, however partially
offset by increased mining losses, as a result of higher slimes at
WCP A. This issue is expected to be resolved by the new WCP A
upfront desliming circuit, which is currently under construction.
As expected, Q4 was the strongest quarter of the year for ore
grades, up 31% compared to Q3 2024, due to WCP B mining an area of
higher grade material.
HMC production in 2024 was 1,446,600 tonnes,
broadly in line with 2023, although with significantly improved
production in H2 (787,600 tonnes versus 659,000 tonnes in H1 2024).
2024 represents a new annual record for excavated ore volumes,
which were up 7% YoY. This partially offset the 5% decrease in ore
grades YoY, as WCP A approaches the end of its mine path in
Namalope.
Kenmare delivered significantly stronger
production of all finished products in Q4 2024 compared to Q4 2023.
Ilmenite production was up 14% to 307,400 tonnes, benefitting from
the 11% increase in HMC processed and higher ilmenite content in
the HMC. Primary zircon production was up 5% due to the higher HMC
processed partially offset by a build-up in intermediate stocks.
Rutile production was up 38% YoY, with December representing a new
monthly record for rutile production. Improvements through 2024
were due to circuit upgrades, which have enabled increased
recoveries. Concentrates production was up 7%, with the increased
HMC processed partially offset by the previously mentioned stock
build and stronger recovery to primary products.
Kenmare exceeded the midpoint of production
guidance for ilmenite in 2024 and the upper end of the guidance
range for primary zircon, rutile and concentrates. Total production
of finished products was 1,115,300 tonnes, up 2% YoY (2023:
1,091,500 tonnes), despite flat HMC processed.
Ilmenite production was 1,008,900 tonnes in
2024, up 2% YoY, benefitting from improved recoveries and higher
ilmenite content in the HMC processed. Primary zircon production
was down 1% YoY due to a build-up of non-magnetic intermediate
stock in Q4, expected to be drawn down in 2025. Rutile production
was up 17% YoY due to improved recoveries following circuit
improvements and concentrates production was up 1%, benefitting
from the production of a new concentrates product that was sold on
a trial basis in Q3. This product will be sold on a commercial
basis in 2025.
Q4 2024 was the strongest quarter of the year
for shipments, with volumes of 308,300 tonnes. Shipments were down
5% YoY, although H2 2024 (611,000 tonnes) was significantly
stronger than H1 2024 (477,600 tonnes). Shipment volumes in Q4 2024
comprised 261,300 tonnes of ilmenite, 30,300 tonnes of primary
zircon, 3,700 tonnes of rutile and 13,000 tonnes of
concentrates.
The product mix was higher value in H2 than H1,
with 42,800 tonnes of primary zircon shipped in H2 (H1: 8,800
tonnes) and 7,400 tonnes of rutile (H1: 0). The product mix in H1
2024 was impacted by two high value zircon shipments being delayed
from June into July and no rutile was shipped in the first half of
the year.
Total shipments in 2024 were 1,088,600 tonnes,
up 4% compared to 2023, supported by increased production of
finished products and benefitting from consistently strong customer
demand. Shipments during the year comprised 989,000 tonnes of
ilmenite, 51,600 tonnes of primary zircon, 7,400 tonnes of rutile
and 40,600 tonnes of concentrates.
Closing stock of HMC at the end of 2024 was
14,100 tonnes, compared with 16,700 tonnes at the start of the
year, due to a small amount of HMC in stock being drawn down for
processing during the year. Closing stock of finished products at
the end of 2024 was 287,200 tonnes, compared with 259,100 tonnes at
the end of 2023. Due to strong production in H2 2024 and high
levels of finished product stock at the end of the first half,
Kenmare had higher than usual levels of finished product stock at
year-end. Shipments are expected to exceed production in 2025 and
drive a reduction in finished product stock levels.
Capital projects update
WCP A upgrade and transition to Nataka
The WCP A project remains on budget, with
upgrade works continuing to advance, thereby progressively
derisking the project. At the end of Q4, 75% of the project budget
had been committed, in line with expectations. WCP A is currently
mining an area 750 metres from the staging pond, which is on track
with the schedule for it to connect with the new module in Q3
2025.
The fabrication of the two new dredges continues
to progress with the project contractor in the Netherlands.
The dredges are expected to be launched into the water at the
contractor’s docks over the coming weeks, with all fabrication
anticipated to complete in Q2. They will then be transported to
Moma by sea for commissioning in Q3.
All of the principal components of the new
module for WCP A, which incorporates 42 pontoons, a surge bin, an
upfront desliming circuit, major steelwork and screens, are now on
site and construction is advancing to schedule, with commissioning
expected in Q3.
Construction of the Tailings Storage Facility
has been impacted by permitting delays associated with the
Mozambique general election. Construction commenced in mid-January,
with commissioning scheduled for Q4. Management of slimes in the
interim period of Q3 has been accommodated within the mine
plan.
Selective Mining Operation (“SMO”)
The introduction of a new small-scale
dredge-mining and concentrating operation, or SMO, will enable
mining in peripheral areas of Mineral Resources in the Pilivili
high dunes and Namalope Flats at the Mine. These areas are low in
slimes, above average grade and not accessible by the larger WCPs
or existing dry mining operations that are limited by groundwater
levels, which prevent the extraction of ore below the water table.
The SMO is expected to produce approximately 50,000 tonnes of HMC
per annum.
The SMO construction process is well advanced at
Moma, with commissioning of the first module of the plant expected
to commence in late January and the second part in February. The
capital expenditure is anticipated to be less than $6 million
and the project remains on budget.
The introduction of the SMO supports Kenmare’s
ability to deliver ilmenite production in 2025 that is broadly in
line with 2023 and 2024 levels, despite the planned downtime for
WCP A required to facilitate the replacement of the dredges and the
upgrade of the plant.
Finance and corporate update
Dividends and year-end cash and debt
On 11 October 2024, Kenmare paid its interim
2024 dividend of USc15.0 per share, representing a total interim
distribution of $13.4 million. The Company expects total dividends
in respect of 2024 to be at the upper end of Kenmare’s dividend
policy payout ratio of 20-40% of profit after tax.
Cash and cash equivalents were $56.9
million at year-end (2023: $71.0 million).
Gross bank loans, including accrued interest, were $80.4 million
(2023: $48.8 million) and lease liabilities were $1.3 million
(2023: $1.5 million). As a result, the Company had net debt of
$24.8 million at year-end (2023: $20.7 million net cash). Supported
by on-going cash generation, available current assets and its
Revolving Credit Facility, Kenmare remains well-capitalised to fund
the WCP A capital project and its dividend programme.
Implementation Agreement
Kenmare has agreed in principle to certain
modifications to the applicable investment regime in connection
with the renewal of rights under the IA and the renewal and
modifications are awaiting consideration at Ministerial level. In
the meantime, the Ministry of Industry and Commerce has
provided confirmation that Kenmare’s existing rights and benefits
remain in full force and effect pending conclusion of the
process.
The original renewal date was 21 December 2024.
However, due to delays associated with the recent Mozambique
general election, the renewal, along with others of a similar
nature, will be matters to be dealt with by the incoming
Government.
A further update on the renewal of the IA will
be provided in due course.
Appointment of Chief Financial
Officer
As announced on 20 December 2024, James
McCullough has been appointed as Kenmare’s Chief Financial Officer
and he will join the Company on 1 May 2025. James brings extensive
mining, strategic and financial experience to Kenmare, having
served for 14 years with Rio Tinto Plc, most recently as
General Manager - Group Strategy. James succeeds Tom Hickey,
who was previously Finance Director before being appointed as
Managing Director in August 2024.
Market update
Kenmare’s shipments increased by 4% in 2024,
reflecting consistently strong customer demand for Kenmare’s
products. However, the average price received decreased compared to
2023, as expected, due to increased supply outweighing demand.
Despite this, the Company believes the fundamentals for its
products are strong, due primarily to medium- and long-term supply
constraints within the titanium feedstocks industry and the
favourable characteristics of its products. Kenmare’s average price
received was stronger in H2 than H1 due to a higher value product
mix in the second half as a result of two zircon shipments being
delayed from June to July.
Global demand for titanium feedstocks reached a
record high during the year, supported by strong demand from
emerging markets such as South America and Asia (excluding China).
The titanium metal market also continued to consume significant
quantities of titanium feedstocks due to its growing
production.
However, supply grew more strongly, with
increased exports of Heavy Mineral Concentrate to China from
Mozambique, Sierra Leone, and Indonesia. This new supply also more
than compensated for the reduced production from mines nearing the
end of their lives.
Kenmare is well-positioned due to the flexible
nature of its ilmenite product suite and its ability to sell its
products into multiple market segments. The Company is a preferred
supplier to the beneficiation market due to the high quality, low
impurity nature of its ilmenite, which achieves a premium in the
market. Most new supply is not suitable for this market segment,
which supports demand for Kenmare’s ilmenite, and it is growing
faster than the global titanium feedstocks market.
Pigment production in China continued at high
levels in 2024, despite proposed anti-dumping duties from the
European Commission. While these regulations reduced Chinese
exports to Europe, China increased its exports to other regions,
such as other Asian countries, largely offsetting this impact.
Pigment production in Europe increased significantly in 2024, as
producers responded to the reduced availability of Chinese pigment.
Both trends also supported demand for Kenmare’s ilmenite during the
year.
2024 was a challenging year for the global
zircon market, impacting Kenmare’s received prices. Although there
was a partial recovery in Q1, underlying demand remained weak due
to softness in China’s construction sector.
2025 guidance
2025 guidance for production and operating costs
is as follows:
|
Unit |
2025 Guidance |
2024 Actual |
Production |
|
|
|
Ilmenite |
tonnes |
930,000-1,050,000 |
1,008,900 |
Primary zircon |
tonnes |
47,500-54,000 |
50,500 |
Rutile |
tonnes |
9,000-10,000 |
9,800 |
Concentrates1 |
tonnes |
63,000-69,000 |
46,100 |
Costs |
|
|
|
Total cash operating costs |
$m |
228-252 |
N/R2 |
Cash costs per tonne of finished product |
$/t |
206-228 |
N/R2 |
- Concentrates include secondary
zircon, mineral sands concentrate and 25,000 tonnes of a new
concentrates product
- To be reported in full year
financial statements.
Ilmenite production in 2025 is expected to be
between 930,000 and 1,050,000 tonnes, with HMC production at a
consistent level throughout the year. Grades are expected to be
higher in H1 than H2, however excavated ore volumes are expected to
increase in H2, largely due to the commissioning of the new higher
capacity dredges at WCP A, offsetting the weaker grade. Finished
product production is expected to be boosted by the addition of
25,000 tonnes of a new concentrates product, which is included in
concentrates production guidance.
Shipments are forecast to exceed production in
2025, supported by high levels of finished product stock.
Total cash operating costs for 2024 are
anticipated to be towards the upper end of guidance ($219-243
million). Full details of 2024 costs will be provided with the 2024
Preliminary Results. Total cash operating costs in 2025 are
anticipated to be broadly in line with 2024 at $228-252
million.
Expenditure on development projects and studies
is expected to be approximately $155 million in 2025, with $150
million relating to the WCP A project. Kenmare guided in July 2024
that capital expenditure on the WCP A project would be $128 million
in 2025. The Company incurred less capital expenditure than
expected in 2024 so a portion of this was deferred to 2025. The WCP
A project remains on budget, with a total cost estimate of $341
million.
Improvement projects are expected to cost $7
million in 2025 and relate to a number of initiatives, including
studies relating to a potential Enterprise Resource Planning system
and upgrades to the Mineral Separation Plant.
Sustaining capital costs in 2025 are expected to
be approximately $38 million. Sustaining capital is typically
approximately $30 million per annum but it is elevated in 2025 due
to the planned five-yearly dry dock of the Peg, one of Kenmare’s
transshipment vessels, and the anticipated purchase of a second
Selective Mining Operation.
Notice of 2024 Preliminary
Results
Kenmare plans to release its 2024 Preliminary
Results on Wednesday, 26 March 2025.
For further information, please contact:
Kenmare Resources plc
Jeremy Dibb / Katharine Sutton
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: +353 87 943 0367 / +353 87 663 0875
Murray (PR advisor)
Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221
About Kenmare Resources
Kenmare Resources plc is one of the world's
largest producers of mineral sands products. Listed on the London
Stock Exchange and the Euronext Dublin, Kenmare operates the Moma
Titanium Minerals Mine in Mozambique. Moma's production accounts
for approximately 7% of global titanium feedstocks and the Company
supplies to customers operating in more than 15 countries. Kenmare
produces raw materials that are ultimately consumed in everyday
quality-of life items such as paints, plastics and ceramic
tiles.
All monetary amounts refer to United States
dollars unless otherwise indicated.
Forward Looking Statements
This announcement contains some forward-looking
statements that represent Kenmare's expectations for its business,
based on current expectations about future events, which by their
nature involve risks and uncertainties. Kenmare believes that its
expectations and assumptions with respect to these forward-looking
statements are reasonable. However, because they involve risk and
uncertainty, which are in some cases beyond Kenmare's control,
actual results or performance may differ materially from those
expressed or implied by such forward-looking information.
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Jan 2025 to Feb 2025
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Feb 2024 to Feb 2025