Rio2 Limited (“Rio2” or the “Company”) (TSXV: RIO; OTCQX: RIOFF;
BVL: RIO), is providing an update on construction activities at its
Fenix Gold Mine located in the Maricunga Gold Belt of the Atacama
Region, in Chile.
OVERVIEW
Pre-construction activities commenced at the
Fenix Gold Mine in 2022 prior to the Environmental Impact
Assessment (“EIA”) for the project being rejected by the Chilean
environmental regulators. Those activities included:
- ordering and securing of long lead
items for the construction of the adsorption, desorption, and gold
recovery (“ADR”) plant and associated infrastructure
- fabrication of ADR plant components
such as tanks and ADR plant foundation footings
- construction of a 565-person camp
and associated mess and office facilities at the Lince
infrastructure site, located 20km from the mine site
- water loading facilities at the
Nueva Atacama water treatment facilities located in Copiapo
The project’s EIA was subsequently approved in
December 2023 following a successful 18-month appeal process.
The Company recommenced construction activities
at the Fenix Gold Mine in October 2024 after successfully
completing a debt and equity financing for the construction of the
mine announced on October 29, 2024.
The projected construction capex for 2025 is
estimated to be USD 122 M (excluding Chilean VAT tax which is
refundable) with construction expected to be completed in November
2025. First gold production is currently guided for January
2026.
PLANT SITE
Bulk earthworks at the plant site have been
completed and concrete bases for the footings of the processing
plant have been poured. The ADR plant will be housed within a steel
framed building cladded with modular thermo-acoustic panels.
LEACH PAD
Earthworks have commenced on the leach pad
stability platform, which forms the base of the Phase 1 leach pad.
The leach pad has been designed to be built in four phases over the
17-year mine life of the 20,000 tonnes per day operations.
PREGNANT LEACH SOLUTION (“PLS”)
POND
Excavation earthworks for the PLS pond have
commenced adjacent to the ADR plant. The PLS pond will be lined
with a double HDPE geomembrane liner system and have an installed
capacity of 28,000 cubic metres. As determined by water balance
modelling in the 2023 Fenix Gold feasibility study, a larger major
events pond is currently planned to be built in year 6 of the mine
operation.
PERSONNEL
The recruitment activities for the Fenix Gold
Mine have focused on hiring key personnel for construction
activities and future mine operation roles. Personnel numbers at
the Fenix Gold Mine are increasing and, currently, over 531 staff
and contractors work on-site. At the end of Q4 2024, approximately
50% of the workforce were from the Atacama region, and 16% of
on-site personnel were women.
SAFETY
At the end of Q4 2024, the project achieved
161,917 person-hours worked with no lost time injuries
reported.
GRADE CONTROL DRILLING AND GEOPHYSICAL
SURVEY
In February, the Company will commence a 12,000m
grade control drilling program focused on the first three years of
production planned from the Fenix South and Fenix North pit areas.
Fenix South will be the first area drilled during the months of
February, March and April, and Fenix North will be drilled in
October and November. The Fenix South pit will be the principal
source of ore for the first year of mine production.
From February to March the Company will complete
a survey of 25,000 meters of CSAMT electromagnetic lines. This
survey will help the geological team identify silicified zones
associated with black banded veins, which are the main gold host at
the Fenix Gold deposit. The geophysical targets generated from this
work will allow the Company to focus its future exploration
drilling campaigns with the objective to grow the mineralized
resource at Fenix Gold. Resource expansion drilling is currently
planned to occur once gold production has commenced at the
mine.
Rio2 is also pleased to announce that Enrique
Garay has recently returned to the Company as Senior Vice President
- Geology to lead and oversee the Fenix Gold geological team in
preparation for mining toward the end of 2025 and future
exploration.
MINE EXPANSION STUDY & ASSOCIATED
EIA
A preliminary internal study completed by the
Rio2 technical team has indicated that the Fenix Gold Mine has the
potential to be expanded from its first phase 20,000 tonnes per day
ore mining rate to around 80,000 tonnes per day. Increasing the ore
mining rate to this level could see gold production rise from an
initial rate of approximately 100,000 oz per annum to a target
range of 250,000 – 300,000 oz per annum. To quantify and justify
this potential expansion, the Company has initiated a mine
expansion study with a target completion date by the end of 2025.
Long-term water options will be assessed for the study and the most
optimal water strategy will be selected and form a base case for
project economics. To put this potential expansion case on a fast
track to a construction decision, Rio2 has recently initiated
baseline studies for an EIA study on the project, which is
anticipated to be ready for review by the environmental regulators
in the Atacama Region by Q4 2026. As most of the required
infrastructure for the expanded project (apart from water which is
expected to be provided by a third-party provider) is within the
existing footprint of the currently approved EIA, the Company
expects the EIA process to advance relatively smoothly. Updates
will be provided as the expansion study and EIA progress.
Andrew Cox, President & CEO, commented,
“Site activities at the Fenix Gold Mine continue advancing to plan.
We are delighted with the team we are putting together and the
milestones achieved so far. We look forward to continued success as
we prepare the mine for first gold production in January 2026.”
Photos of the construction activities can be
found at (https://www.rio2.com/media/photos).To view a 3D VRIFY
version of Rio2’s corporate presentation please click the following
link: https://vrify.com/decks/17439 or visit the
Company’s website at www.rio2.com
STOCK OPTION GRANT
The board of directors of the Company has
approved the grant of an aggregate of 6,310,000 incentive stock
options (the “Options”), pursuant to the Company’s Stock Option
Plan, to a total of 72 directors, officers and employees of the
Company, its Peruvian subsidiary, Rio2 S.A.C., and its Chilean
subsidiaries, Fenix Gold Limitada and Lince S.A. The Options are
exercisable at a price of $0.70 per share (based on a 10% premium
over the closing price of C$0.63 on January 10, 2025) and will
expire five years from the grant date. The Options represent the
Company’s annual grant of long-term incentives consistent with the
Company’s regular yearly compensation.
FENIX GOLD PROJECT
The Fenix Gold Project is one of the largest
undeveloped gold oxide, heap leach projects in the Americas,
hosting a Measured and Indicated mineral resource (as such term is
defined in National Instrument 43-101 -Standards of Disclosure for
Mineral Projects, “NI 43-101”) of 4.8 million ounces of gold which
the Company believes will make a positive contribution to the
Atacama Region and Chile. The Project is an example of modern gold
mining where a full complement of technical, environmental, and
social considerations has been consulted and designed from the
outset. The Project represents a significant investment in the gold
mining business in Chile by a junior mining company of
approximately US$235M of initial and sustaining capital, generating
employment for at least 1,200 people during the construction phase
and 550 people during the 17-year operations phase. The mine being
contemplated will be a run-of-mine heap leach operation; no
crushing or tailings storage facilities are required, thereby
minimizing the overall impact and footprint of the Project.
The scientific and technical content of this
news release has been reviewed, approved and verified by Enrique
Garay, MSc P.Geo/FAIG who is a QP under NI 43-101. For additional
information regarding the Project, including key parameters,
assumptions and risks associated with its development, see the
independent technical report entitled “NI 43-101 Technical Report
on the Feasibility Study for the Fenix Gold Project” (the
“Feasibility Study”) pursuant to National Instrument 43-101
Standards of Disclosure for Mineral Projects (“NI 43-101”). The
Feasibility Study is dated October 16, 2023, with an effective date
of October 16, 2023, a copy of which document is available under
Rio2’s SEDAR+ profile at www.sedarplus.ca.
ABOUT RIO2 LIMITED
Rio2 is a mining company with a focus on
development and mining operations with a team that has proven
technical skills as well as successful capital markets track
record. Rio2 is focused on taking its Fenix Gold Project in Chile
to production in the shortest possible timeframe based on a staged
development strategy. Rio2 and its wholly owned subsidiary, Fenix
Gold Limitada, are companies with the highest environmental
standards and responsibility with the firm conviction that it is
possible to develop mining projects that respect the three pillars
(Social, Environment, Economics) of responsible development. As
related companies, we reaffirm our commitment to apply
environmental standards beyond those that are mandated by
regulators, seeking to protect and preserve the environment of the
territories that we operate in.
Forward-Looking Statements
This news release contains forward-looking
statements and forward-looking information (collectively
“forward-looking information”) within the meaning of applicable
securities laws relating to Rio2’s development of the Fenix Gold
Project and other aspects of Rio2’s future operations and plans.
In addition, without limiting the generality of the foregoing, this
news release contains forward-looking information pertaining to
the following: the development of a mine at the Project and related
construction activities; the expected capital required for such
mine; the expected timing of the first pour of gold; estimated
indicated and measured gold resources; expected mine life;
development and operating plans and expenditures; certain
anticipated economic benefits of a mine at the Project to the local
region; the potential to expand production from the first stage
mining rate and associated gold production along with the timing
for the completion of related studies and approvals; and other
matters ancillary or incidental to the foregoing.
All statements included herein, other than
statements of historical fact, may be forward-looking information
and such information involves various risks and uncertainties.
Forward-looking information is often, but not always, identified by
the use of words such as “seek”, “anticipate”, “plan”, “continue”,
“estimate”, “expect”, “may”, “will”, “project”, “predict”,
“potential”, “targeting”, “intend”, “could”, “might”, “should”,
“believe” and similar expressions. The forward-looking information
is based on certain key expectations and assumptions made by Rio2’s
management, including but not limited to: expectations concerning
prevailing commodity prices, exchange rates, interest rates,
applicable royalty rates and tax laws; capital efficiencies;
legislative and regulatory environment of Chile; future mining and
production rates and estimates of capital and operating costs;
expectations regarding the availability of debt financing;
estimates of reserves and resources; anticipated timing and results
of capital expenditures; the sufficiency of capital expenditures in
carrying out planned activities; results of operations;
performance; the anticipated timing and results of expansion
studies and related approvals; the availability and cost of
financing, labor and services; and Rio2’s ability to access capital
on satisfactory terms.
Rio2 believes the expectations reflected in
these forward-looking statements are reasonable, but no assurance
can be given that these expectations will prove to be correct and
such forward-looking statements in this news release should not be
unduly relied upon. A description of assumptions used to develop
such forward-looking information and a description of risk factors
that may cause actual results to differ materially from
forward-looking information can be found in Rio2's disclosure
documents on the SEDAR+ website at www.sedarplus.ca. These risks
and uncertainties include, but are not limited to: risks and
uncertainties relating to the completion of debt and equity
financing for the construction phase of the mine, market conditions
and management’s ability to anticipate and manage the factors and
risks referred to herein.
Forward-looking statements included in this news
release are made as of the date of this news release and such
information should not be relied upon as representing its views as
of any date subsequent to the date of this news release. Rio2 has
attempted to identify important factors that could cause actual
results, performance or achievements to vary from those current
expectations or estimates expressed or implied by the
forward-looking information. However, there may be other factors
that cause results, performance or achievements not to be as
expected or estimated and that could cause actual results,
performance or achievements to differ materially from current
expectations. Rio2 disclaims any intention or obligation to update
or revise any forward-looking statements, whether as a result of
new information, future events or otherwise, except as expressly
required by applicable securities legislation.
To learn more about Rio2 Limited, please visit:
www.rio2.com or Rio2's SEDAR+ profile at www.sedarplus.ca.
ON BEHALF OF THE BOARD OF RIO2
LIMITED
Alex BlackExecutive Chairman Email:
alex.black@rio2.comTel: +51 99279 4655
Kathryn Johnson Executive Vice President, CFO
& Corporate Secretary Email: kathryn.johnson@rio2.comTel: +1
604 762 4720
Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts the responsibility for the adequacy
or accuracy of this release.
Rio2 (TSXV:RIO)
Historical Stock Chart
From Dec 2024 to Jan 2025
Rio2 (TSXV:RIO)
Historical Stock Chart
From Jan 2024 to Jan 2025